West London faces 13-year new homes ban as electricity grid reaches capacity

A potential ban on new housing projects until 2035 may come into effect for developers as the electricity grid has run out of capacity to support additional homes.

In a message to developers, the Greater London Authority warned that it might take over a decade to increase the grid capacity to a sufficient level to enable developments to start again in the west London boroughs of Hillingdon, Ealing and Hounslow.

According to the GLA’s note, shared by the Financial Times: “Major new applicants to the distribution network…including housing developments, commercial premises and industrial activities will have to wait several years to receive new electricity connections.”

With the three boroughs making up almost 11% of London’s housing supply in 2019-20, the ban would w

London currently faces a housing shortage problem, with delivery targets regularly not being met, so any ban would only exacerbate the existing issue for years to come and jeopardise housebuilding targets further. The three boroughs made up almost 11% of London’s housing supply in 2019-20, and this figure was set to increase with major developments planned in the areas.

The GLA said that the building of a number of data centres built over recent years had put pressure on the grid in west London, using the equivalent amount of electricity as a town or small city to power servers.

Work is underway by SSEN and National Grid to upgrade their networks to cope with the additional demand, but it could take several years to fully implement.

David O’Leary, policy director of the Home Builders Federation, said: “[Developers are] still getting their heads around this, but our basic understanding is that developments of 25 units or more will be affected. Our understanding is that you just can’t build them.”

He went on to say that the GLA’s message had already led one HBF member to reconsider the purchase of a plot of land for development in Ealing. O’Leary also expects the problem to become more widespread, with rules now in place that require new homes to support low-carbon technologies, all of which place additional strain on the grid.

The GLA, SSEN and the National Grid are working together to find a solution that will unblock development. This will include installing cables to connect developments to less-constrained grids, reviewing the needs of individual customers and incentivising electricity usage at low-demand times.

The GLA has not yet responded when requested to comment by the Financial Times.