The delivery of at least 17,432 affordable homes has ground to a halt as the lack of interest from Registered Providers, according to the HBF

17,000 affordable homes stalled by lack of bids from housing associations

The delivery of at least 17,432 affordable housing units with detailed planning permission has ground to a halt as the lack of Registered Providers participating in the market is threatening supply, new research reveals.

A study published by the Home Builders Federation shows that at least 139 home-building sites are currently delayed due to uncontracted Section 106 (S106) units.

The current affordable housing delivery model now accounts for around 44% of all new affordable homes that are being delivered. Yet, recent years have seen a gradual reduction in the number of RPs actively bidding for S106 Affordable Homes, as a result of the economic and policy challenges facing the affordable housing sector.

The ‘Bid Farewell’ report finds 136 sites across the country are currently delayed, forcing developers to re-evaluate the pace and direction of their building programmes, which could pose a threat to the future of businesses and overall housing output.

Without a contracted 106 deal, small builders are often unable to secure the development finance to start a development, whilst larger sites can be stalled because the planning permission requires the affordable element of the site to be delivered by a certain trigger point. As a result, both private and affordable housing delivery is being slowed or stalled.

Many factors lead to uncontracted affordable homes but, if left unaddressed, this issue could lead to further delays, therefore jeopardising the housing pipeline and undermining the government’s target of delivering 1.5 million homes during this Parliament.

The HBF is calling for housing associations to be put on a firm financial footing to enable them to confidently take on the affordable housing delivered by housebuilders. It also calls for greater flexibility to be built into the process behind the delivery of affordable homes.

Neil Jefferson, chief executive at the Home Builders Federation, said: “The lack of Registered Providers in the market to take on the affordable housing delivered by the private sector is a major and growing problem, increasingly threatening affordable and overall housing supply.”

“Small sites are being prevented from starting, and larger sites are being halted due to the inability of developers to meet the affordable housing delivery requirements of the planning permission.

“Following very positive government statements about its ambitious targets and welcome changes to planning rules, home builders are eager to invest and increase output. However, the inability to discharge affordable housing obligations, coupled with a lack of affordable mortgages suppressing private sales, is holding back housing supply increases.”